50 PMP Exam Practice Questions (2026) – Free PMP Certification Quiz with Answers

PMP exam practice questions with answers 2026

Preparing for the PMP exam in 2026? This free practice test gives you 50 original PMP exam practice questions with instant answers and explanations, organized around the official PMP Examination Content Outline domains: People, Process, and Business Environment. Whether you're a project manager studying for your first attempt or revisiting weak areas before exam day, this quiz is built to mirror the scenario-based style of the real PMP certification exam.

The Project Management Professional (PMP)® credential, issued by the Project Management Institute (PMI)®, remains one of the most recognized project management certifications in the United States, United Kingdom, and globally. Unlike simple recall-based tests, the PMP exam is heavily situational — it tests how you would act as a project leader, not just what a term means. That's exactly the format used in the questions below.

50
Questions
Intermediate
Difficulty
35 min
Est. Time
PMP Exam Prep
Best For
2026
Updated
📚 What You Will Learn in This Quiz
  • ✔ Handling team conflict & disagreements
  • ✔ Stakeholder engagement strategies
  • ✔ Servant leadership & emotional intelligence
  • ✔ Earned value metrics (CPI, SPI, EAC)
  • ✔ Critical path & schedule analysis
  • ✔ Risk, quality & procurement processes
  • ✔ Agile, hybrid & predictive approaches
  • ✔ Benefits realization & compliance
Advertisement

PMP Exam Format Overview (2026)

Before diving into the practice questions, here's a quick refresher on what to expect on exam day. PMI updates exam specifics periodically, so always confirm the latest details on the official PMI website before you book your exam.

Exam DetailOverview
Total QuestionsApproximately 180 questions
Time Limit230 minutes (with two scheduled breaks)
Question TypesMultiple choice, multiple response, matching, hotspot, and limited fill-in-the-blank
Domains TestedPeople (~42%), Process (~50%), Business Environment (~8%)
Delivery MethodComputer-based testing (test center or online proctored)
Approach MixPredictive, agile, and hybrid project management approaches
Advertisement

People Domain Questions (1–21)

PEOPLE DOMAIN · ~42% OF EXAM

This domain focuses on leading teams, resolving conflict, building a collaborative environment, and supporting team performance — skills that apply whether you're running a predictive, agile, or hybrid project.

1. Two senior team members have a disagreement about the technical approach for a deliverable, and the conflict is starting to affect team morale. What should the project manager do first?

  • A) Make the technical decision yourself to end the disagreement quickly
  • B) Ask both team members to discuss the issue privately and bring you a joint recommendation
  • C) Escalate the disagreement to the sponsor for resolution
  • D) Ignore it since technical disagreements usually resolve on their own
Show Answer

Correct Answer: B — Encouraging the individuals to resolve the issue collaboratively respects their expertise and autonomy. The PM facilitates rather than dictates, escalating only if collaboration fails.

2. A team member consistently misses internal deadlines but delivers high-quality work. The project manager wants to address this without damaging motivation. What is the best approach?

  • A) Publicly call out the missed deadlines in the next team meeting
  • B) Reassign all of that person's future tasks to someone else
  • C) Hold a private conversation to understand the root cause and agree on a plan together
  • D) Report the pattern directly to HR for performance review
Show Answer

Correct Answer: C — A private, supportive conversation uncovers root causes (workload, unclear priorities, personal issues) and preserves trust, which is more effective than punitive or public action.

3. A distributed team works across three time zones, and team members report feeling disconnected from project goals. What technique would most directly improve this?

  • A) Send a single weekly status email to everyone
  • B) Establish overlapping core hours and regular video check-ins
  • C) Require all team members to relocate temporarily
  • D) Reduce the size of the team to limit time zone spread
Show Answer

Correct Answer: B — Overlapping core hours and consistent video touchpoints build connection and shared understanding for virtual or distributed teams, directly addressing the disconnect.

4. A project manager notices that one stakeholder's needs have not been addressed in the stakeholder engagement plan. What should the PM do?

  • A) Proceed without updating the plan since the project is already underway
  • B) Update the stakeholder engagement plan and re-assess the stakeholder's influence and interest
  • C) Remove the stakeholder from future communications
  • D) Wait until the next phase gate review to address it
Show Answer

Correct Answer: B — Stakeholder engagement is iterative. Newly identified gaps should be reflected in the stakeholder register and engagement plan as soon as they're discovered.

5. Which leadership style is most associated with removing obstacles for the team and prioritizing their needs over directing tasks?

  • A) Autocratic leadership
  • B) Transactional leadership
  • C) Servant leadership
  • D) Laissez-faire leadership
Show Answer

Correct Answer: C — Servant leadership is centered on serving the team by removing impediments, coaching, and prioritizing their growth and success — a core mindset in agile and modern PMP thinking.

6. A new team member is unfamiliar with the project's established ground rules and unintentionally disrupts a planning session. What should the project manager do?

  • A) Remove the team member from future planning sessions
  • B) Privately review the ground rules with the new member and clarify expectations
  • C) Publicly correct them during the session to set an example
  • D) Ignore the disruption since it was unintentional
Show Answer

Correct Answer: B — A private, respectful clarification of expectations helps the new member integrate without embarrassment, supporting a psychologically safe team environment.

7. During a sprint, a team member raises an impediment that requires support outside the team's authority. What is the Scrum Master's or project manager's primary role here?

  • A) Solve the technical problem personally
  • B) Escalate and actively work to remove the impediment so the team can continue
  • C) Tell the team to work around it independently
  • D) Document it and revisit it at the next retrospective
Show Answer

Correct Answer: B — Actively removing impediments — especially those beyond the team's control — is a core servant-leadership responsibility, keeping the team unblocked and productive.

8. A project manager wants to increase psychological safety so team members feel comfortable raising bad news early. Which action best supports this goal?

  • A) Penalizing missed estimates in performance reviews
  • B) Responding to raised issues with curiosity and problem-solving rather than blame
  • C) Requiring written justification for every delay
  • D) Limiting issue reporting to monthly status reports only
Show Answer

Correct Answer: B — Responding to problems constructively, without blame, encourages early and honest disclosure of risks and issues — which is far more valuable than discovering them late.

9. A team is newly formed and members are still uncertain about their roles and how to work together. According to Tuckman's stages of team development, what stage is this?

  • A) Performing
  • B) Norming
  • C) Forming
  • D) Adjourning
Show Answer

Correct Answer: C — "Forming" is the initial stage where team members are getting acquainted and roles are not yet clearly established.

10. A key stakeholder consistently disengages from project communications despite high influence on project success. What is the most appropriate engagement strategy?

  • A) Stop sending them updates since they don't respond
  • B) Move them to a lower-priority engagement category permanently
  • C) Identify the reason for disengagement and tailor a more relevant communication approach
  • D) Ask another stakeholder to represent their interests instead
Show Answer

Correct Answer: C — For high-influence stakeholders, the PM should investigate the disengagement and adapt the communication method, format, or frequency to re-engage them rather than disregarding them.

11. Which conflict resolution technique involves both parties giving up something to reach a mutually acceptable resolution?

  • A) Forcing
  • B) Compromising
  • C) Withdrawing
  • D) Collaborating
Show Answer

Correct Answer: B — Compromising means each party concedes something to reach a solution that partially satisfies both sides, unlike collaborating, which seeks a full win-win outcome.

12. A project manager wants to delegate more decision-making authority to the team to increase ownership. What is this approach called?

  • A) Micromanagement
  • B) Empowerment
  • C) Risk transfer
  • D) Resource leveling
Show Answer

Correct Answer: B — Empowerment involves giving team members the authority and trust to make decisions within their area of work, increasing engagement and accountability.

13. During a retrospective, the team identifies that unclear requirements caused rework. What should happen next?

  • A) Note it informally and move on to the next sprint
  • B) Agree on a specific, actionable improvement and assign ownership for it
  • C) Assign blame to the business analyst
  • D) Escalate to the sponsor immediately
Show Answer

Correct Answer: B — Retrospectives are only valuable when they produce concrete, owned action items — not just discussion. This drives continuous improvement.

14. A project manager observes that a high-performing team member is being given a disproportionate workload because others assume they'll "just handle it." What should the PM do?

  • A) Let it continue since it's getting results
  • B) Quietly give that person a bonus instead
  • C) Rebalance task assignments and address the underlying team dynamic
  • D) Remove the person from the project to protect them
Show Answer

Correct Answer: C — Sustainable team performance requires fair workload distribution. The PM should address both the immediate imbalance and the team behavior causing it.

15. Which of the following best demonstrates emotional intelligence in project leadership?

  • A) Making all decisions based purely on data, ignoring team sentiment
  • B) Recognizing a team member's frustration and adjusting your communication approach accordingly
  • C) Avoiding difficult conversations to keep morale high
  • D) Treating all team members identically regardless of context
Show Answer

Correct Answer: B — Emotional intelligence is the ability to recognize emotions (in yourself and others) and adapt your behavior — exactly what's described in option B.

16. A cross-functional team includes members from different cultural backgrounds, and a misunderstanding occurs due to differing communication norms. What is the best first step?

  • A) Standardize all communication to one cultural norm
  • B) Facilitate an open discussion to build mutual understanding of communication preferences
  • C) Separate the team members involved into different workstreams
  • D) Document the misunderstanding for the lessons-learned register only
Show Answer

Correct Answer: B — Open dialogue about communication norms builds cultural awareness and prevents recurring misunderstandings in diverse teams.

17. What is the primary purpose of a team charter?

  • A) To define the project's budget and schedule baseline
  • B) To establish team values, agreements, and operating guidelines
  • C) To list all project risks
  • D) To document the procurement strategy
Show Answer

Correct Answer: B — A team charter establishes shared values, communication norms, decision-making processes, and conflict resolution methods for the team.

18. A sponsor wants to bypass the team and assign tasks directly to individual developers. What should the project manager do?

  • A) Allow it since the sponsor has authority
  • B) Have a direct conversation with the sponsor about the impact on team accountability and project flow
  • C) Instruct the developers to ignore the sponsor's requests
  • D) Resign from the project
Show Answer

Correct Answer: B — The PM should proactively manage this stakeholder relationship, explaining how direct task assignment undermines prioritization, accountability, and team workflow.

19. Which negotiation approach seeks a solution where all parties' underlying interests are satisfied, rather than just their stated positions?

  • A) Positional bargaining
  • B) Principled negotiation
  • C) Hardball tactics
  • D) Avoidance
Show Answer

Correct Answer: B — Principled negotiation (interest-based bargaining) focuses on underlying needs and interests rather than rigid positions, typically producing more durable agreements.

20. A team member asks the project manager for mentorship to grow into a leadership role. What is the most effective approach?

  • A) Tell them to read a leadership book on their own time
  • B) Give them stretch assignments and provide regular coaching feedback
  • C) Promote them immediately to validate their interest
  • D) Decline since mentoring isn't part of the PM's role
Show Answer

Correct Answer: B — Effective mentorship combines real growth opportunities (stretch assignments) with ongoing, constructive coaching — this is part of a PM's people-leadership responsibility.

21. What is the most appropriate way to handle a team member who is a strong individual performer but resists collaborating with others?

  • A) Remove them from the team immediately
  • B) Have a candid conversation linking collaboration to team and project success, and set clear expectations
  • C) Allow them to work in isolation permanently since their output is good
  • D) Assign all their work to other team members instead
Show Answer

Correct Answer: B — Addressing the behavior directly, with clear expectations tied to team outcomes, balances respecting individual strengths with the need for collaborative delivery.

Advertisement

Process Domain Questions (22–46)

PROCESS DOMAIN · ~50% OF EXAM

This is the largest domain on the exam, covering scope, schedule, cost, quality, risk, procurement, and agile/hybrid delivery mechanics.

22. A project's Cost Performance Index (CPI) is 0.85. What does this indicate?

  • A) The project is ahead of schedule
  • B) The project is under budget
  • C) The project is over budget — earning less value per dollar spent than planned
  • D) The project is exactly on budget
Show Answer

Correct Answer: C — A CPI below 1.0 means the project is spending more than the value of work completed, indicating a cost overrun.

23. The Schedule Performance Index (SPI) for a project is 1.15. What does this mean?

  • A) The project is behind schedule
  • B) The project is ahead of schedule
  • C) The project is exactly on schedule
  • D) The schedule baseline needs to be re-approved
Show Answer

Correct Answer: B — An SPI greater than 1.0 means more work has been completed than planned at this point — the project is ahead of schedule.

24. On a network diagram, Activity A has zero total float, while Activity B has 3 days of total float. What does this tell the project manager?

  • A) Activity A is on the critical path; Activity B is not
  • B) Both activities are on the critical path
  • C) Activity B is more important to monitor
  • D) Activity A can be delayed without affecting the project end date
Show Answer

Correct Answer: A — Activities with zero float lie on the critical path; any delay there delays the whole project. Activity B has slack and is not critical.

25. The Estimate at Completion (EAC) using the formula EAC = AC + (BAC − EV) is most appropriate when:

  • A) Future cost variances are expected to continue at the current rate
  • B) Future work will be completed at the planned budgeted rate, regardless of current performance
  • C) The project is being re-baselined entirely
  • D) There is no remaining work left to estimate
Show Answer

Correct Answer: B — This EAC formula assumes that current variances were atypical and that remaining work will proceed at the original planned rate.

Advertisement

26. A risk has a 30% probability of occurring and would cause a $50,000 cost impact if it does. What is the Expected Monetary Value (EMV) of this risk?

  • A) $50,000
  • B) $15,000
  • C) $30,000
  • D) $35,000
Show Answer

Correct Answer: B — EMV = Probability × Impact = 0.30 × $50,000 = $15,000.

27. A risk response strategy where the project team takes specific action to reduce the probability or impact of a negative risk is called:

  • A) Risk acceptance
  • B) Risk transfer
  • C) Risk mitigation
  • D) Risk avoidance
Show Answer

Correct Answer: C — Mitigation reduces the probability and/or impact of a risk, as opposed to avoidance (eliminating the risk entirely) or transfer (shifting it to a third party).

28. During project execution, a new risk is identified that was not in the original risk register. What should the project manager do?

  • A) Ignore it since risk identification is only done during planning
  • B) Add it to the risk register and assess it through qualitative/quantitative analysis
  • C) Wait for the next phase gate to log it
  • D) Immediately implement a contingency reserve without analysis
Show Answer

Correct Answer: B — Risk identification and analysis are iterative throughout the project life cycle, not a one-time planning activity.

29. Which procurement document is used to formally request detailed proposals, including technical approach and price, from potential sellers?

  • A) Request for Information (RFI)
  • B) Request for Quotation (RFQ)
  • C) Request for Proposal (RFP)
  • D) Purchase Order (PO)
Show Answer

Correct Answer: C — An RFP requests a comprehensive proposal covering approach, qualifications, and pricing, used when the solution requires more than just a price comparison.

30. In a fixed-price contract, who bears the greater financial risk if costs run over budget?

  • A) The buyer
  • B) The seller
  • C) Both parties equally
  • D) Neither — costs are automatically passed to the customer
Show Answer

Correct Answer: B — In fixed-price contracts, the seller is obligated to deliver at the agreed price, so cost overruns are absorbed by the seller.

31. A change request is submitted mid-project to add new functionality. What is the correct next step before implementing the change?

  • A) Implement it immediately since the customer requested it
  • B) Submit it through the integrated change control process for evaluation and approval
  • C) Add it informally to the backlog without documentation
  • D) Reject it automatically since it wasn't in the original scope
Show Answer

Correct Answer: B — All formal changes should go through integrated change control, where impact on scope, schedule, cost, and risk is assessed before approval.

32. What is the main purpose of a Work Breakdown Structure (WBS)?

  • A) To assign individual task deadlines
  • B) To decompose project scope into manageable, deliverable-oriented components
  • C) To track team member performance
  • D) To calculate the project's critical path
Show Answer

Correct Answer: B — The WBS breaks total project scope into smaller, manageable components organized around deliverables, forming the foundation for planning and control.

33. In an agile project, who is primarily responsible for prioritizing the product backlog?

  • A) The Scrum Master
  • B) The development team
  • C) The Product Owner
  • D) The project sponsor
Show Answer

Correct Answer: C — The Product Owner owns the product backlog and is responsible for prioritizing items based on business value and stakeholder needs.

34. A team's velocity has been steadily decreasing over the last three sprints despite stable team composition. What should be investigated first?

  • A) Whether the team needs to be replaced
  • B) Whether impediments, technical debt, or scope complexity are slowing delivery
  • C) Whether the sprint length should be doubled
  • D) Whether the Product Owner should be removed
Show Answer

Correct Answer: B — A declining velocity trend with a stable team usually points to underlying issues like unresolved impediments or growing technical debt, which should be investigated through retrospectives.

35. What is the primary purpose of a sprint review in Scrum?

  • A) To assign tasks for the next sprint
  • B) To inspect the increment and gather stakeholder feedback
  • C) To evaluate individual team member performance
  • D) To finalize the project budget
Show Answer

Correct Answer: B — The sprint review is held at the end of a sprint to inspect the completed increment and collect stakeholder feedback to inform future backlog priorities.

Advertisement

36. A project follows a hybrid approach: predictive for hardware procurement and agile for software development. What is the main reason for this approach?

  • A) Hybrid approaches are always required by PMI
  • B) Different components of the project have different levels of certainty and change frequency
  • C) It eliminates the need for a project schedule
  • D) It avoids the need for stakeholder engagement
Show Answer

Correct Answer: B — Hybrid approaches match the delivery method to the nature of the work — predictive for well-defined, low-change components and agile for components with evolving requirements.

37. Quality control identifies a defect rate exceeding the acceptable threshold defined in the quality management plan. What should the project manager do first?

  • A) Close the project phase regardless
  • B) Investigate the root cause using tools such as a fishbone diagram
  • C) Immediately replace the quality assurance team
  • D) Lower the quality threshold to match current performance
Show Answer

Correct Answer: B — Root cause analysis (e.g., a fishbone/Ishikawa diagram) should be used to understand why defects are occurring before deciding on corrective action.

38. What is the difference between quality assurance and quality control?

  • A) They are the same process with different names
  • B) Quality assurance is preventive and process-focused; quality control is inspection-focused on deliverables
  • C) Quality control happens only during planning
  • D) Quality assurance is performed only by external auditors
Show Answer

Correct Answer: B — Quality assurance focuses on improving processes to prevent defects, while quality control involves inspecting actual deliverables for defects.

39. A project requirement is found to be ambiguous after development has already started. What is the best course of action?

  • A) Make an assumption and proceed without informing the stakeholder
  • B) Pause and clarify the requirement directly with the relevant stakeholder
  • C) Cancel the related deliverable entirely
  • D) Let the team interpret it independently to save time
Show Answer

Correct Answer: B — Ambiguous requirements should be clarified directly with stakeholders to avoid costly rework from incorrect assumptions.

40. What document formally authorizes the existence of a project and gives the project manager authority to use organizational resources?

  • A) Project Management Plan
  • B) Business Case
  • C) Project Charter
  • D) Scope Statement
Show Answer

Correct Answer: C — The project charter formally authorizes the project and grants the project manager authority over assigned resources.

41. A project is closing, and several lessons learned were identified during execution. What should happen to this information?

  • A) It should be discarded since the project is complete
  • B) It should be documented and added to the organizational process assets for future projects
  • C) It should only be shared verbally with the next project manager
  • D) It should be kept confidential within the project team
Show Answer

Correct Answer: B — Lessons learned should be formally documented and stored as organizational process assets to benefit future projects.

42. A stakeholder requests a status update outside the agreed communication schedule. What is the best response?

  • A) Refuse since it's outside the communication plan
  • B) Provide a brief update and consider whether the communication plan needs adjustment
  • C) Ignore the request
  • D) Forward the request to the sponsor without responding
Show Answer

Correct Answer: B — Being responsive to genuine stakeholder needs while reassessing whether the communication plan should be updated balances flexibility with process discipline.

43. In earned value management, what does "Planned Value (PV)" represent?

  • A) The actual cost incurred to date
  • B) The authorized budget for the work scheduled to be completed by a specific point in time
  • C) The value of work actually completed
  • D) The total budget at completion
Show Answer

Correct Answer: B — Planned Value is the budgeted cost for work scheduled to be done by a given date — it represents the plan, not actual performance.

44. A project team uses a Kanban board to visualize workflow. The "Work in Progress" (WIP) limit for the development column is consistently exceeded. What is the best response?

  • A) Increase the WIP limit permanently to match current behavior
  • B) Investigate why items are accumulating and address the bottleneck before adjusting limits
  • C) Remove the WIP limit entirely
  • D) Assign more people to the testing column instead
Show Answer

Correct Answer: B — WIP limits exist to surface bottlenecks. The team should investigate and resolve the underlying constraint rather than simply raising the limit.

45. What is the primary benefit of using rolling wave planning on a project with evolving requirements?

  • A) It eliminates the need for a schedule altogether
  • B) It allows near-term work to be planned in detail while future work is planned at a higher level until more is known
  • C) It guarantees the project will finish early
  • D) It removes the need for stakeholder input
Show Answer

Correct Answer: B — Rolling wave planning provides detailed planning for near-term work while leaving distant work at a summary level, refined as more information becomes available.

46. A project manager discovers that a deliverable does not meet the acceptance criteria defined by the customer. What should happen next?

  • A) Deliver it anyway to maintain the schedule
  • B) Address the gap through the validate scope process before seeking formal acceptance
  • C) Lower the acceptance criteria to match the deliverable
  • D) Escalate directly to the steering committee without investigation
Show Answer

Correct Answer: B — Validate Scope ensures deliverables meet acceptance criteria before formal sign-off; gaps should be resolved through this process, not bypassed.

Advertisement

Business Environment Questions (47–50)

BUSINESS ENVIRONMENT · ~8% OF EXAM

This smaller domain tests how well you connect project work to organizational strategy, compliance, and benefits realization.

47. A project is technically successful, but six months after delivery, the organization has not seen the expected increase in revenue. What is the most likely gap?

  • A) The project management plan was incomplete
  • B) Benefits realization was not actively tracked and managed after project closure
  • C) The team lacked technical skills
  • D) The risk register was not updated
Show Answer

Correct Answer: B — Delivering outputs is not the same as realizing business benefits. Benefits realization must be actively tracked, often beyond project closure, to confirm the business case value is achieved.

48. New government data privacy regulations are introduced mid-project, affecting how customer data can be stored. What should the project manager do?

  • A) Ignore it since it wasn't part of the original scope
  • B) Assess the compliance impact and update the project plan and risk register accordingly
  • C) Wait until the next audit cycle to address it
  • D) Delegate the decision to the development team without further analysis
Show Answer

Correct Answer: B — External compliance and regulatory changes must be assessed for impact and incorporated into the project plan and risk management approach promptly.

49. A project's deliverables require a significant change in how end users perform their daily work. What discipline helps ensure successful adoption?

  • A) Earned value management
  • B) Organizational change management
  • C) Procurement management
  • D) Configuration management
Show Answer

Correct Answer: B — Organizational change management addresses the people side of change — communication, training, and adoption — which is critical when deliverables alter established ways of working.

50. A project aligns well with the organization's current strategic plan, but that strategic plan is being revised by leadership. What should the project manager do?

  • A) Continue exactly as planned since the charter has already been approved
  • B) Proactively engage with the sponsor to understand how the strategic shift may affect project priorities or scope
  • C) Pause the project indefinitely without confirmation from leadership
  • D) Make unilateral scope changes to match anticipated strategy
Show Answer

Correct Answer: B — Projects must stay aligned with organizational strategy. Proactively engaging with the sponsor ensures the project adapts appropriately if strategic direction changes, without making unauthorized changes.

Advertisement
🎯 Check Your Score
45 – 50
🏆 Excellent — Exam Ready
35 – 44
👍 Very Good — Almost There
20 – 34
💪 Good — Keep Practising
Below 20
📖 Study the Basics Again

📊 How did you score? Share your result in the comments and let us know which domain you'd like a deeper practice test on next — People, Process, or Business Environment.

Frequently Asked Questions About the PMP Exam

How many questions are on the PMP exam?

The PMP exam currently consists of approximately 180 questions, combining multiple choice, multiple response, matching, and hotspot question formats. Always verify the current format on PMI's official website, as exam specifications can be updated.

What is a good score on this practice test?

Since PMI does not publicly disclose an exact passing score, treat this practice test as a diagnostic tool rather than a pass/fail predictor. Scoring 80% or higher across all three domains is generally a strong indicator of readiness, but focus more on understanding why an answer is correct than on the score itself.

Which domain should I focus on most while studying?

Process carries the most weight (around 50% of the exam), so it deserves the most study time. However, many candidates underestimate the People domain (around 42%), which tests situational judgment heavily — this practice test deliberately weights questions to reflect that real exam balance.

Is this practice test affiliated with PMI?

No. This is an independently created study resource designed to help candidates practice scenario-based thinking similar to the real exam. It is not officially affiliated with, endorsed by, or sponsored by the Project Management Institute.

About the Author

My Name is M. Zahid, I have master degree in Computer Science. Currently I am working as an Information Technology Teacher in Govt sector of Pakistan. Blogging is my passion and I try my best to deliver some useful contents on our blogs for my res…

Post a Comment

Do Not Enter any Link, All comments checked before published.
Oops!
It seems there is something wrong with your internet connection. Please connect to the internet and start browsing again.